What this work covers
Protection work creates a continuous barrier along the lift, corridor, entry, retained floors, frames, cabinets, fixtures, and non-work areas. It protects them from material movements, demolition impact, dust, and contamination, and it must remain intact as the construction stages change.

When this work is needed
Install protection before deliveries, demolition, carpentry, or any dusty or high-impact work when finishes or occupied areas will remain. Even a full strip-out still leaves shared corridors, the entry door, windows, and other retained elements exposed, so do not judge the protection scope by the demolition plan alone.
Decide before work starts
Map the protected route and retained elements before selecting the materials.
- The building's required protection materials and coverage for the lift, corridor, and entry
- Retained floors, frames, windows, cabinets, and sanitary fixtures inside the property
- Temporary partition locations between work and non-work areas
- Delivery routes and the corners, thresholds, and controls most likely to be struck
- Who inspects the protection and replaces damaged material during the project
Check in the quote
Use these questions when you review the quote.
- Are the shared-area and internal coverage and materials specified separately?
- Does the protection include lift controls and corners, the entry door, and frames?
- Are temporary partitions and dust-sealing tape included?
- Does the price include replacement and reinspection as the finishing stages change?
- Is removal and disposal of the protection defined after demolition or completion?
If you have site photos or a protection quote, I can help you trace the route from shared areas to retained finishes and identify missing coverage.
What to check on site
Protection is more than a sheet laid on the visible floor. The whole material route, every retained finish, and the edge of the dusty work area need to read as one continuous protective line.
- Prepare protection scope and materials

Compare the building standard with the demolition and retention drawings, then mark every surface from the lift to the working area. Use load-bearing material on floors and impact-absorbing protection on frames and corners rather than covering everything with the same thin plastic. - Protect shared areas

Reinforce lift walls and controls, corridor corners, and entry thresholds before joining the floor protection without gaps. Push a loaded cart through the actual route to confirm that seams do not lift, roll back, or expose the finish below. - Protect inside the unit

Inside the property, separate retained finishes and excluded areas, and seal the temporary partition where it meets floors and walls. If protection becomes wet or torn, remove it, inspect the finish below, and replace it rather than hiding the damage under another layer.
Where problems usually start

- Lift walls, floor, and controls Partial coverage leaves surfaces exposed to tools and material edges, leading to scratches and claims from building management.
- Seams in floor protection A lifted seam or weak covering exposes retained timber or tile to impact and abrasion.
- Edges of temporary partitions Unsealed floor and wall junctions allow demolition dust to pass into storage or occupied areas.
If water or dust is found below the protection, do not add another layer on top. Remove the cause, inspect the retained finish, and then reinstate the barrier.
Photograph the same positions before work, after installation, and at trade changes. These matched records make responsibility clearer if protection is later damaged or a retained finish is scratched.
Timing and records
Installation currently takes about half a day to one day, depending on the protected area and the number of temporary partitions. Include reinspection at major deliveries and trade changes rather than treating protection as a one-time task.
Keep the building standard, photos of every retained finish before work, completed protection in shared and private areas, and each damage and replacement record. These are the main references when a scratch or contamination claim is assessed later.
Protection follows site setup and establishes the routes that safety preparation and layout work must preserve. Looking at them together keeps protected finishes, deliveries, and emergency access from competing for the same space.