What this work covers
Site setup provides the temporary power, lighting, water, washout point, access control, and clear movement routes that every trade needs. Each temporary service is tested under real use before the main work begins.

When this work is needed
Set up the site before demolition, carpentry, tile, painting, or any sequence that brings several workers, power tools, temporary lighting, or water into the property. A short repair may use the existing services, but only after confirming that the circuits and taps are suitable and that key control and end-of-day shutdown are clearly assigned.
Decide before work starts
Fix the locations and operating rules before the first trade arrives.
- The circuits used, cable-reel ratings, and residual-current protection points
- Temporary lights for the main work faces and safe cable routes
- The temporary water connection, hose route, washout point, and drainage
- The key-safe location, code, and authorised users
- Who isolates power and water at the end of each working day
Check in the quote
Use these questions when you review the quote.
- Are temporary power, lighting, and cable reels included?
- Who checks residual-current protection and reel capacity?
- Does the setup include the water connection, leak test, washout area, and drainage?
- Who controls the key safe and access record?
- Who completes the daily power and water shutdown check?
If you have a floor plan or start-of-work photos, I can help you check the temporary power, water, delivery, and working routes.
What to check on site
Good setup keeps movement, power, water, and access from creating new hazards for one another. Establish the delivery and waste route first, then place and test every temporary service around it.
- Confirm temporary locations and paths

Clear the material-delivery and waste-removal route before locating cable reels, work lights, temporary water, and the key safe. Fix cables and hoses along the wall or protect crossings so they do not become trip or impact hazards. - Install temporary power and lighting

Separate temporary power by the circuits that will supply the actual tools and test the residual-current protection. Switch on the work lights to check for deep shadows at cutting and drilling faces, and do not run high-load tools while the cable remains coiled on the reel. - Set temporary water and access

Run water through the temporary connection and all the way to the washout drain to test both supply and disposal. Limit the key code to authorised workers, and record where the final worker isolates power and water in the daily handover.
Where problems usually start

- Overloaded cable reel Several power tools on one reel can overheat the cable and increase the risk of a short circuit or fire.
- Temporary water connection An unsecured hose or untested fitting can separate under pressure and cause water damage to the property below.
- Key safe and access rights Sharing the location and code too widely increases the risk of lost keys and unauthorised entry.
If a cable reel becomes hot or the breaker trips repeatedly, do not simply replace it with a larger reel. Recalculate the demand of each tool and distribute the load across suitable circuits.
If water appears around the temporary connection, close the valve immediately. Check the fitting and drainage route and inspect for damage below before restoring the supply.
Timing and records
Allow about half a day for setup, but the condition of the existing services and the site route can change this. Before the main work starts, prove that the power, water, lighting, and access process all work in practice.
Record the circuits used, reel ratings, protection test, hose connections and water-test result, key-safe location, and shutdown responsibility. Temporary services move throughout the project, so the daily inspection record should move with them.
Site setup follows the measured survey and gives protection and safety work a real route to follow. Looking at those stages together prevents temporary services from cutting across protected or emergency paths.